SAVE THE DATE: Pool resurfacing/painting Sept 6-10

It has been 6+ years since we painted the pool last which equates to 7 pool seasons.  As with any paint job there is quite a bit of prep work and will require 2 coats of paint.  I am putting the proposed schedule here so we can start planning and volunteers can add to their calendar.

Here is the proposed schedule but will be dependent upon volunteers and weather conditions at the time.

Wed, Sept 6 (need 4 volunteers):

  • Pressure wash loose paint.
  • Replace hydrostatic relief valve in deep end.
  • Repair broken and loose tiles.
  • Start time:  late afternoon
  • Approx time:  4 hours

Thurs, Sept 7: (need 4-6 volunteers):

  • Acid wash the pool.
  • Start time:  late afternoon
  • Approx time:  4 hours

Fri, Sept 8: (need 6-8 volunteers):

  • Paint
  • Start time:  morning
  • Approx time:  4 hours

Sat, Sept 9(need 6-8 volunteers):

  • Paint
  • Start time:  morning
  • Approx time:  4 hours